We (my dad and I) poured the first wall of the carriage house today. I figured for 3.5 yards which involved a bit of guestimation, given the fact that the stones we were pouring the concrete on were all varying sizes. In the end we ended up with about 5 wheelbarows extra. Plenty of margin.
It took me right at 3 hours to finish the concrete once we (dad) floated it. I did a border around the windows with some stone finish mats I had made, and the rest of it with a rock salt finish. (Not sure how the transition between the two finishes will look, but this carriage house is the experiment to prove and improve the methods.)
more later….